Phase II Photo Journal

Watch the progress in completing Phase II of our school building at 11111 Bren Road W.

- Schedule a Tour! -

Click Here to Learn More about the Phase II Project

Phase II Photos:

June 16: Construction is continuing well! Walls are painted and hallways are being completed. Demo for the auditorium has begun. View newest photos in our Facebook photo album!

-----------------------------------------------------------------------------------------------------------------------

May 18: Classrooms are beginning to take shape! If you'd like to see the work in person, sign up for a tour (offered every Thursday through the end of the school year).

Below: completed drywall along the north hallway.

Below: drywall installation and ceiling installation in existing rooms. 

Below: drywall progress and flooring material delivery in the main commons.

Below: paint and ceiling grid in the west art classroom. 

Below: paint process in the main commons. 

Below: flooring installation in west art room. 

-----------------------------------------------------------------------------------------------------------------------

March 25: Almost all of the walls for the new classrooms have been framed. 

-----------------------------------------------------------------------------------------------------------------------

March 1: Construction officially begins today!

-----------------------------------------------------------------------------------------------------------------------

Jan. 30: Demolition in the second level is complete. The space is largely empty and ready to be turned into classrooms, hallways, offices, and community gathering areas! The skylight outside the gym commons will become the main staircase to the second level.